FLOOD
Project: Bollington – Macclesfield – 2019
Appointment
- Health & Safety Consultant
- CDM Advisor
Scope of Work
- Emergency installation of temporary stone ballast gabions, in 1- ton bags to retain existing stone wall, undermined by strong, rapid river currents during heavy rainfall event
Significant Hazards
- Work at Height
- Lifting Operations
- Working above water
- Road Closure
- Fall Arrest System with Davit Arm
Project: The Daffodil Hotel & Spa – Grasmere – 2016
Appointment
- Health & Safety Consultant
- CDM Advisor
- Site Safety Inspections
Scope of Work
- Strip out & reinstatement of flood damaged hotel and spa at the ground floor level
Significant Hazards
- Occupied premises with staff
- Site Traffic Management
- Decontamination
- Temporary Electrics
Project: Standfast & Barracks – Lancaster – 2015
Appointment
- Principal Designer
- CDM Advisor
- Environmental Advisor
- Health & Safety Consultant
- Site Safety Inspections
Scope of Work
- Storm Eva, heavy rainfall flooding events during late Winter 2015 and early 2016; leading to reinstatement of textile and fabric printing business; established in 1924
Significant Hazards
- Chemicals
- Asbestos Containing Materials
- Operational Plant
- Drainage
- Logistics
- Fire Evacuation
- Hazardous Substances
Project: Windermere Marina Village – Bowness on Windermere – 2009
Appointment
- Health & Safety Consultant
- Site Safety Inspections
Scope of Work
- Strip out & reinstatement of flood damaged hotel and spa at the ground floor level
Significant Hazards
- Occupied premises with staff
- Site Traffic Management
- Decontamination
- Temporary Electrics